- well, we dropped by before work this morning to confirm which toilet bowls and sinks go to which bathroom... but they'll work on it tomorrow
- The metal/iron sections of our perimeter fencing have been installed
- Air-cons have been delivered yesterday and installed by this afternoon
- Our stainless steel stairs railings and main door handles had also been delivered today - they're likely to be installed tomorrow
- Perimeter fencing lights have been partially installed
- cabinets for the kids rooms have been completed & delivered, but not installed yet (Henry has his own furniture factory, so we had our closets and cabinets custom built, as with all the doors)
- The water tank and water heater support is also ready - waiting for final coat of paint and the stainless steel tank to be installed
- Ball is in our court though for the driveway and main entrance floor - another long drive to Bandar again to choose the tiles, and hope to have it done by midweek next week
metal fencing installed. contractor painted the leaves in green when we wanted black/gold - they'd rectify it soon (they say it should be easy)