Anyway, updates!
- Floor tiles: All ground floor tiled except Dry Kitchen & Guestroom.
- Fencing: Main concrete structures all done. Plastering almost done, but they still need to do some design on the fence.
- Wooden floor: they have polished the floor during the week and also puttied (for lack of words) the gaps between the woods.
- Window: they have already installed the handles (today i think, cos I didn't see it yesterday)
- Ceilings: all covered, except for the entrance foyer where they'll install the dome.
- Doors: The PVC door frames for Family Room and Dining Room have been installed. Wooden doors? the design for the doors was only passed to Henry last Sunday, and he'll have his carpenters make a sample for our review before he make the others.
- Cornice: Only the master bedroom done so far.
- Cabinets: They've installed the cabinets in Master Suite & the girls' room walk-in-closet, and at Muhammad's room
- Mains: cable has been installed from main supply to the gate and to the house.
Phew! That's a lot of updates.... and now for the pics. To my friends who frequent my blog (including my HSE adviser - you know who you are), apologies for delay in updating. For GoKuQal, ada udah tu gambar kitchen. Enjoy the pics and enjoy your weekend!
Pics above and below proves that not much changes can be expected outside. Pic above taken on Monday, 28 Jan.
View from the entrance steps. You can see the bar /island in the horizon as well as the gap in the ceiling waiting for the dome